Phase Two Teller Street Alley Paving Project

The Town of Frisco and Columbine Hills Concrete will be starting phase two of the Teller Street alley paving project. Teller Street alley will be paved from 3rd Avenue to 5th Avenue.

Work is scheduled to start the week of June 24th and be completed within 45 days. During construction there will be no parking allowed in the alley and daytime closures may be expected. Some overnight closures will also take place to allow the concrete to cure properly.

The Town regrets any inconvenience caused by this work and hopes this will be offset by the improved conditions in the alley.

If you have any questions, please call Brad Thompson, Frisco Streets Foreman, at 970-668-9154.